Decide which service you actually need
IESCO applicants: IESCO’s official website says its new-connection service has moved from ENC to e-OPS. It directs applicants to the Power Smart app, IESCO Smart app or nearest Customer Facilitation Center. Check the current IESCO application notice before following the general ENC steps below.
A first electricity connection, a name change and a load change are different requests. Start with the service available for your provider on the official ENC portal. If your provider or request is not listed, follow the utility’s published application instructions instead.
Prepare the address, intended connection use, requested load and applicant information carefully. The required evidence depends on the service, premises and applicant’s relationship to the property. Do not submit a generic downloaded checklist without checking the current portal instructions.
Build a document checklist from the application
| Item to verify | Why it matters |
|---|---|
| Applicant identity | The application must identify the person making the request. Use the identity documents the official form asks for. |
| Property / occupancy evidence | Ownership, tenancy or authorisation circumstances can require different supporting documents. |
| Connection purpose and load | The requested category and approved load affect technical and billing treatment. |
| Location and contact details | Use an accurate service address and reachable contact information. |
| Provider-specific attachments | Follow the current ENC or utility checklist, including any declarations or required attestations. |
Submit identity and property documents only to the official provider process. PakistanBillCheck does not receive, verify or store application documents.
Where to check the requirements yourself
The November 2025 Consumer Service Manual places new-connection applications in section 2.2, supporting documents in section 2.3, the application form in Annex I and load-category timeframes in Annex III. It provides for an acknowledgement and tracking or case ID. Read the relevant category and any later amendment instead of applying one installation deadline to every connection.
Follow the application through its stages
- Apply through the official routeChoose the correct provider and service, complete the fields and upload what that application requests.
- Keep the tracking recordSave the application/tracking number and submitted copy. This is separate from a future electricity reference number.
- Respond to document or technical queriesReview the official status and provide corrections through the designated channel. Keep copies of any response.
- Handle a demand notice if issuedCheck its account/application details, amount, validity and authorised payment method. Retain the receipt and upload/submit proof where instructed.
- Wait for the provider’s remaining processA paid demand notice is not a promise that a meter is installed immediately. Technical approval, work and connection activation remain provider responsibilities.
Do not pay an intermediary solely because they promise an immediate meter or claim they can bypass the official process. Use documented charges and the provider’s authorised payment instructions.
Track the exact application, not a bill lookup
ENC tracking and duplicate-bill lookup solve different tasks. If no electricity bill exists yet, repeatedly entering an application number into a bill form will not create a result. Use the tracking number in the official application service.
If a status is unclear, ask for the outstanding step and any missing document rather than assuming rejection or approval. A fixed installation deadline or universal connection fee is not quoted here because the category and current process matter.
Ask a question that matches the stalled stage
| Last record you have | Ask for this next piece of information |
|---|---|
| Submitted form, but no acknowledgement | Whether the application was received and which tracking/case ID identifies it. |
| Tracking ID and a document query | Which requested item is missing or unreadable and how to resubmit it against the same case. |
| Demand notice, not yet paid | Its validity, authorised payment route and whether its details match the application. |
| Payment receipt, status not updated | Whether the receipt was matched to the case and what verification remains. |
| Provider says work is complete, no usable supply | The activation/metering record and the proper service follow-up for the site. |
Record the date, channel, reply and next action alongside the same tracking ID. That log gives a later complaint a specific unresolved step rather than only saying “my connection is delayed”.
Common problems to avoid
- Selecting a provider from a broad city guess instead of checking the application service.
- Using a tariff category that does not match the intended connection.
- Uploading unreadable or incomplete documents.
- Confusing a demand-notice receipt with completed installation.
- Losing the tracking number and starting another application without checking the first.
Questions you may have
Can I submit my documents to this website?
No. Use the official ENC or provider process. This page is a preparation guide.
Is a paid demand notice the same as an active connection?
No. Keep the payment record and follow the provider’s remaining approval and installation steps.
Sources & scope
The sources below explain the service or rule discussed on this page. Use your provider’s records for an individual account.
- ENC: Electricity New Connection portalApplication and tracking entry point; use the service and provider options actually available.
- NEPRA: revised Consumer Service Manual, November 2025Sections 2.2–2.3; Annex I application form and Annex III timeframes. Read with later amendments in the legal register.
- NEPRA: Consumer Service Manual and amendmentsCheck for changes to the named manual before using a requirement.